Pressure washing on units 58-62 will be starting tomorrow, Wednesday, August 8th. Prep work, caulking, and priming is occurring on 43-52. Second coat on cedar shakes on 14-26 being completed. Second coat on units 14-26 nearing completion. These units will be ready for final inspection by Tony next Tuesday.
Greg
Operations